Korea Electric Power Co. Completes ACCC® Reconductor Project

Written by Dave Bryant

August 5, 2022

With the support of Contractor SD Energy Co., Ltd, Korea Electric Power Company (KEPCO) doubled the capacity of two circuits on their Jecheon – Sinjecheon 154 kV Transmission line in Chungbuk, Korea. KEPCO chose Brussel size ACCC® Conductor manufactured by CTC Global’s authorized ACCC® Manufacturing Partner, ILJIN Electric Co., Ltd Korea.

The ACCC® Conductor was installed on existing steel lattice structures – without modification – on spans ranging from 184 meters to 410 meters. While the hilly terrain required a number of equipment relocations, the project was completed very quickly without issues. CTC Global’s Master Installer Mr. Mark Eglinton & Mr. Yi, Apprentice Master Installer were onsite to support the project’s success.