Southern Power Project Management Board (SPPMB) Completes ACCC® Installations in Vietnam

ACCC® Installations in Vietnam – To increase the capacity, efficiency, and reliability of their 220 kV Thot Not – Long Xuyen – Chau Doc transmission lines, SPPMB installed 284 kilometers of ACCC® Conductor in the Can Tho and An Giang Provinces of Vietnam. SPPMB selected ACCC® Conductor Warsaw size conductor manufactured by PT KMI Wire & Cable. The 46.4 ckm project was completed in three sections, energized in March, June, and July.
 
Existing steel lattice structures were used without modification with spans ranging from 350 to over 420 meters. The lines crossed over several waterways with very wet working conditions. The PCC1 construction crew used twin pullers and tensioners. PLP supplied ACCC® Conductor Hardware. ACCC Master Installers Tiep and Truong provided installation support.